A commercial entrance permit in Kentucky is issued by the Transportation Cabinet, not by the city or county planning office, whenever the driveway you intend to use touches a state-maintained highway. That single fact reorders a Lexington commercial deal, because the approval you need most is the one nobody in the local permit office can give you. This is the pre-offer version of that reading.
Who issues a commercial entrance permit in Kentucky?
The Department of Highways district office for the county the access point sits in. Not the planning commission, and not the building inspector.
Kentucky’s access rules live in 603 KAR 5:120, Access control of highways. Section 4(2) of that regulation puts the application with “the department’s district office for the county in which the requested access point is located.” For Fayette County and its neighbours that office is Kentucky Transportation Cabinet District 7 in Lexington. The procedural detail sits in the Cabinet’s own Permits manual, which is a public document and worth having open before you write an offer.
The practical test is simple and it is not about city limits. Ask which agency maintains the road your entrance will meet. Nicholasville Road, Richmond Road, Versailles Road and Winchester Road are state routes inside Lexington. An interior subdivision street or a local street is usually not. A parcel can sit entirely inside the urban service boundary, be perfectly zoned, and still have its only usable entrance under state jurisdiction.
What is in the application package?
A signed form, a drawing set, a traffic control plan, and — when indemnity is required — a bond. District 7 publishes the list.
| Item | What District 7 states |
|---|---|
| Application form | Completed and signed Encroachment Permit Application, Form TC 99-1A, submitted electronically as a PDF |
| Supplemental documents | Detailed plans, drawings, traffic control plan, submitted as PDFs |
| Indemnity, when required | Encroachment Permit Bond Form TC 99-7, or a cashier’s check payable to the Kentucky State Treasurer; a bond must be accompanied by a notarised power of attorney |
| Indemnity amount | Varies, and is related to the amount of impact on right of way |
| Internal tracking | Applications are not logged into the Kentucky Encroachment Permit Tracking (KEPT) system for internal review until all documents are received |
| Utility locates near state infrastructure | District 7 requires 3 to 5 business days to complete locate requests |
Read the KEPT sentence twice. The clock a buyer cares about does not start when the engineer emails the form. It starts when the last document lands. An incomplete package is not a slow application; for scheduling purposes it is not an application at all.
Zoning tells you what you may build. The entrance permit tells you whether anyone can get to it.
Can the state simply refuse a new entrance?
On some routes, effectively yes. 603 KAR 5:120 sorts highways into three access categories, and the category decides whether a new access is even on the table.
Under Section 3 of the regulation, highways are access by permit, fully-controlled, or partially-controlled. On a fully-controlled highway, Section 3(2) states that additional accesses “shall be granted only by constructing new interchanges.” On a partially-controlled highway, Section 3(3)(b) sends new access to the criteria established by KRS 177.315, including minimum spacing. Where access is by permit, the criteria in 603 KAR 5:150 govern approval.
There is one more clause in that regulation a buyer should price. Section 4(6) requires the applicant to compensate the Department of Highways for any increase in value to the affected property attributable to the new access, and to reimburse administrative expenses. A new curb cut on a state route is a thing of value, and the regulation says so in writing.
How far apart must entrances be?
By statute, 1,200 feet in rural areas and 600 feet in urban areas. KRS 177.315(2) sets those minimum spacing figures for partial control of access.
“Urban” is not a judgement call. 603 KAR 5:120, Section 1(10) defines it as areas of residential, commercial or industrial development of sufficient concentration that they are characteristic of a city and that necessitate, for safety reasons, reduced highway speed limits of forty-five (45) MPH or less, excluding interstate speed limits. Section 1(9) then defines “rural” as all areas other than urban. So the posted speed limit on the frontage is the practical test, and the difference between a 45 MPH frontage and a 55 MPH frontage is the difference between a 600-foot and a 1,200-foot spacing requirement against the next access point.
Subsection (3) of the statute leaves a door open: the Transportation Cabinet may change the spacing of access control points if the abutting owner or a local government requests it and the change is supported by an engineering and traffic study approved by the state highway engineer. That is a real path, but it is an engineering submission, not a conversation — price it and time it accordingly.
What happens if an entrance was built without a permit?
A seven-day removal order and escalating civil fines. KRS 177.106 governs encroachments on a state-maintained right-of-way, and it reaches work a previous owner did.
The statute defines “encroachment” broadly: any improvement to land including but not limited to buildings, fences, ditches, embankments, driveways or signs, or any change from the original contour of land, that is constructed under, on or over the right-of-way of a state-maintained road and may hinder or prevent use or maintenance of the road. A driveway cut, a culvert, a regraded shoulder and a monument sign all fit.
Where the Department of Highways determines an unpermitted encroachment interferes with the safe, convenient and continuous use and maintenance of a road, it issues a notice of violation and an order to remove or relocate within seven (7) days, at the responsible party’s expense. If that deadline passes, the department causes the removal itself and recoups the cost from the responsible party.
The civil fines escalate: five hundred dollars ($500) for a first violation, one thousand dollars ($1,000) for a second within a three-year period, and two thousand dollars ($2,000) for a third or subsequent violation within three years. After a third violation inside three years, the party is barred from receiving an encroachment permit from the department for six (6) months from the date of the third notice — which on a site whose use depends on a new access point is the consequence that matters far more than the money. The statute also makes the responsible party liable, within twenty-four (24) hours of notice, for any safety measures the department deems necessary. Those fines are collected by the municipality in which the violation occurred and used by it for public safety or infrastructure purposes. This version took effect June 29, 2021 by 2021 Ky. Acts ch. 148, sec. 1.
For a buyer, this converts an existing unpermitted entrance from a cosmetic question into a dated liability with a six-month exposure attached. Ask whether the entrance on the ground matches a permit on file before the offer, not after — and if it does not, a six-month permit bar is a closing-date problem, not a punch-list item.
What does the permit itself cost the owner?
More than a filing fee. Under 603 KAR 5:120 the owner may have to compensate the state for the value the new access adds to the property.
The regulation provides that, prior to issuance of the permit, the owner of the property shall compensate the Department of Highways for any increase in value to the affected property attributable to the new access, based on before-and-after value appraisals by the Department of Highways. The owner also reimburses the department for administrative expenses incurred in processing the permit, the reviews, the hearing and the appraisals, and the cost of construction and maintenance sits with the owner as well.
There is also a hearing step. Where the State Highway Engineer recommends approval of a permit request on a highway with full or partial access control, the commissioner must provide an opportunity for a public hearing held in accordance with 600 KAR 1:030; after reviewing the results, the Commissioner of Highways makes the final decision. A pro forma underwriting line for “entrance permit” does not cover an appraisal-based payment to the Commonwealth plus a public hearing calendar.
What should this change about your offer?
Three things: who you ask, when you ask, and what your contingency actually covers.
First, the question to ask before the offer is whether the existing entrance is permitted and whether your intended use changes it. An entrance built for a single-family dwelling or a farm is not an entrance built for a commercial user, and a change in use is the trigger for a new application rather than a grandfathered pass. Second, a due-diligence period written around local approvals alone can expire while a state review is still open. Third, a general “subject to permits” clause rarely names the right agency. Naming District 7 and Form TC 99-1A in the contingency is free; discovering them in week six is not.
It also interacts with the local track rather than replacing it. Access layout feeds the site plan, the site plan feeds Lexington’s final development plan approval, and the parking count that plan has to show is set by Lexington’s commercial parking requirements. Change the entrance and the circulation changes; change the circulation and the parking layout can change with it. Signage has its own separate municipal track, covered in the note on Lexington sign permits for commercial property.
One observation from reading these files
My habit on any commercial parcel with frontage on a numbered route is to establish the road’s maintaining agency before I look at anything else in the file, because that one answer tells me which rulebook the deal is actually under. It takes a phone call. The pattern I keep seeing in commercial due diligence generally is not that buyers ignore permits — they research the permits their last deal needed. A right-of-way review is the most commonly missing item in that habit, because residential and in-town infill transactions rarely surface it, and nothing in a title commitment or a zoning letter flags it. The cheapest version of this work happens before the offer, when the answer can still change the price.
Questions buyers ask
Does an existing commercial driveway need a new permit when the building changes hands?
A sale by itself is not the trigger. A change in the type or intensity of use, or any relocation or alteration of the entrance, is what sends you back to the district office. Confirm the specific parcel with District 7 rather than assuming the existing cut transfers with your plans.
How long does an encroachment permit review take?
The Cabinet does not publish a single commercial review time, and anyone who quotes you one is guessing. What District 7 does publish is that nothing enters the KEPT review queue until every document is in, and that locate requests near state infrastructure need 3 to 5 business days.
Who pays to build the entrance?
The applicant. Beyond construction, 603 KAR 5:120 Section 4(6) requires compensation to the Department of Highways for any increase in property value attributable to the new access, plus reimbursement of administrative expenses. Budget the permit as a cost line, not a formality.
Last updated: October 27, 2026
By Marcos Gil, REALTOR® — Keller Williams Commonwealth · KY Real Estate License No. 296259 · Call or text (859) 310-1209.
This article is general information about a state permitting process, not legal or engineering advice and not a prediction of any permit outcome. Verify current requirements and forms with Kentucky Transportation Cabinet District 7 before relying on them.